Alliance Altyn launches opencast mining
Overburden operations began at the Jerooy gold deposit.
Overburden operations began at the Jerooy gold deposit.
According to the production and technical department of Alliance Altyn LLC, drilling of the 1st block at the horizon of 3760-3752 in the amount of 5 thousand cubic meters is being completed. Work at the facility is ongoing around the clock.
By the end of 2019, the company plans to carry out overburden operations in the amount of 257.4 thousand cubic meters and begin to mine ore for the mill.
Reserves will be mined in the upper part of the ore body of the North-West section in accordance with the approved technical design and the license agreement.
For mining, the company uses high-performance Caterpillar, Atlas Copco (Epiroc), Terex, Dressta equipment.
News
IBC Presented Its Approaches to Advancing Business Interests at the CIPE Regional Conference
IBC presented Kyrgyzstan’s experience in business advocacy at the CIPE regional conferenc…
From Dialogue to Projects: Central Asia–Central Europe Cooperation Discussed in Prague
On September 19, IBC Executive Director Askar Sydykov participated in the international c…
IBC Members Receive Ministry of Economy and Commerce Awards on Kyrgyzstan’s Entrepreneurs’ Day
On 18 September 2026, the Ministry of Economy and Commerce of the Kyrgyz Republic held an…
Business Community Meets with the UK Ambassador-Designate to the Kyrgyz Republic
On 16 September 2026, the International Business Council, jointly with the British Embass…